🔹Updated Schedule🔹 Road Rehab Project
  • Monday 11/6/23- 1.5” Milling and 8” Patching on Bridgeport Dr. and Lindsey Neal Dr. Proof Roll for 8am on Morgan Rd.
  •  Tuesday 11/7/23- 1.5” and 8” Patching on Bridgeport Dr. and Lindsey Neal Dr. Temp Sign installation on Denham Rd. and Lovett Rd. (Lovett signs will be covered)
  •  Wednesday 11/8/23- 2” Milling on Denham Rd.
  •  Thursday 11/9/23- 2” Milling on Denham Rd. and 15” Premixing on Denham Rd.
  •  Friday 11/10/23- 1.5” Asphalt on Morgan Rd, 2” Milling on Denham Rd., and 15” Premixing on Denham Rd.